Softener Manufacturing Plant
Project Description
The purpose of this project was to construct a new softener manufacturing facility on an area of approximately 5,500 m2 within the existing plant. The project houses all the facilities required for the planned production including:
• Making Building: one-storey high, air conditioned, steel-structured space divided into few separated functional spaces for batch making system, raw material staging, buffer tanks and workshop.
• Packing building: one-storey high, air conditioned, steel-structured space divided into few separated functional spaces for packing and warehouse.
• Utilities building: two levels, subject to future expansion up to four levels including transformers in the ground floor, ring main unit and medium & low voltage panels in the first floor, compressed air unit in the second floor, and chillers & cooling towers on the roof.
• Administration building: two levels, subject to future expansion up to 4 levels including IT room, Quality Assurance labs, 2 meeting rooms that could be converted to one larger room, 2 huddle rooms, breakout area, toilets (for 20 permanent workers), and office spaces accommodating 15 persons.
• Tank farm, which has reinforced concrete foundation to support the tanks. ECG used Revit BIM Package throughout the design process.
- Client
Procter & Gamble
- Location
- Sector
- Project Status
Completed
- Share This Project