Automatic Fire Fighting System for Alamein Field
Aiming to protect El-Hamra Oil Field, located in Alamien; ECG will work on the engineering design for fire alarm and firefighting systems.
The Project comprises the following:
10 Storage tanks
- 1 tank; 100,000 bbl
- 4 tanks; 30,000 bbl
- 1 tank; 10,000 bbl
- 4 tanks; 9,000 bbl
Process area consist of
- 4 Oil Separators
- 1 Heater Unit
- Power Station
- Warehouse/Stores
- Kitchen
- Administration Building
- Accommodation Buildings
- Workshops
- Mess Hall
- Production facilities at; north east Alamien field (each 1000 bbl crude oil tank).
ECG scope covers, detailed design and basis of report.