Automatic Fire Fighting System for Alamein Field

Aiming to protect El-Hamra Oil Field, located in Alamien; ECG will work on the engineering design for fire alarm and firefighting systems.

The Project comprises the following:

10 Storage tanks

  • 1 tank; 100,000 bbl
  • 4 tanks; 30,000 bbl
  • 1 tank; 10,000 bbl
  • 4 tanks; 9,000 bbl

Process area consist of

  • 4 Oil Separators
  • 1 Heater Unit
  • Power Station
  • Warehouse/Stores
  • Kitchen
  • Administration Building
  • Accommodation Buildings
  • Workshops
  • Mess Hall
  • Production facilities at; north east Alamien field (each 1000 bbl crude oil  tank).

ECG scope covers, detailed design and basis of report.