River Nile Protection and Development Project

Project Description

Funded by the Canadian International Development Agency (CIDA), the River Nile Protection and Development (RNPD) project aimed at achieving rational utilization of available resources, mitigation of side effects and increasing the efficiency and effectiveness of present use and future development of the River Nile Channel and its two branches, namely, Damietta and Rosetta. The River Nile Protection and Development (RNPD) Project comprised various tasks and subtasks including:

  • Preparing pre-feasibility studies, designs and tender documents for the optimum alternative concerning the following:
    • Protection of the Nile and its main structures from bed degradation and bank erosion.
    • Preparing an acceptable and implementable pollution control system.
    • Hydropower generation in existing and/or proposed barrages and head regulators.
    • River training and navigation improvements.
    • Utilization of surplus releases and flows that exceed consumption requirements.
  • Development and implementation of computer programs for monitoring changes in riverbeds and banks, predicting the impact of new projects, and for pollution control.
  • Studying and designing civil works required for stabilizing the river regime, navigable channel and riverbanks in critical areas upstream of Assiut Barrage. Also, designing the civil, mechanical and electrical works required for reducing the organic pollution in drained water to allow its re-use in irrigation.
  • Implementing two pilot projects, one to stabilize the riverbanks and the other to treat drained water for reuse in irrigation purposes.
  • Pre-feasibility study for the development of Naga Hammadi Barrage. The study aimed at investigating present conditions of the Barrage, and immediate maintenance needs to guarantee conditions service, in addition to providing conceptual design and cost estimates for rehabilitation works. The possibility of constructing a new barrage was also studied.

Ministry of Water Resources and Irrigation

Completed

Activities

Scope

Studies

Institutional Strengthening

Feasibility Studies

Design

Tender Documentation