Master Plan for East Cairo Potable Water Transmission Mains
Project Description
Potable Water Master Plan for East Cairo:
East Cairo cities and urban communities: Administrative Capital, area bounded to the south by the Cairo Sokhna Road, to the north by Ismailia Canal, to the east by 10th Ramadan City, Badr City and the Provincial Ring Road and to the west by the Ring Road. Intake area of the New Cairo water treatment plants on the banks of the River Nile in Tura, and proposed pipeline routes extending from the intake to the proposed water treatment plant in the Administrative Capital.
Master Planning Services:
- Data collection and verification for the water treatment plants, mains and secondary distribution networks, transmission mains and tanks, in collaboration with the council of each city, the New Urban Communities Authority and the Greater Cairo Water Company.
- GIS maps showing pipeline diameters up to 600 mm for the cities covered by the master plan: New Cairo, Administrative Capital, Al Obour 10th Ramadan, Al Shorouk, Badr, and Al Mostakbal.
- Population studies for the cities covered by the study (10 million inhabitants).
- Identifying current and expected water demand for the stages of the study and specifying the target year.
- Development of the network hydraulic model for East Cairo cities and urban communities for integration with the system of digital maps and GIS programs. The hydraulic model based on the latest versions of maps by the Cairo Utility Data Centre through the Construction Authority for Potable Water and Wastewater.
- Full description of required works and suggestions of implementation. This includes the identification of
- development elements based on the results of the integrated hydraulic analysis of the networks and their accessories (pump stations, tanks)
- Structural master plan for the main lines illustrating the method of supplying cities with potable water. Based on a master plan for transmission lines and treatment plants leading to the transmission mains feeding the cities and hydraulic analysis of transmission mains
- General description of treatment plants and transmission mains: pump capacities for required demands.
- Proposed primary routes of mains and their alternatives and location of proposed treatment plants and transmission mains.
- Proposed primary routes and alternatives for the mains to connect a number of treatment plants together, in accordance with the routes available for East Cairo the cities and urban communities.
- Final master plan report and cost estimates of proposed works up to the target year.
- Identification of high priority projects and cost estimates.
- Client
Construction Authority for Potable Water and Wastewater
- Location
- Sector
- Project Status
Completed
- Share This Project