Project Description

The project involves the development of the original plans drafted for the terminal building of Capital International Airport; the terminal building comprises a ground floor and mezzanine with a total built-up area of 4,250 m2.

Overall works in the airport cover the construction of 30 buildings and facilities of various built-up areas, along with associated infrastructure and landscaping works:

  • Airport maintenance building (340 m2)
  • Airport waste building (107 m2)
  • Fire-fighting building (1,280 m2)
  • Air traffic control tower (853 m2)
  • Airfield lighting system building (240 m2)
  • 2 Airfield lighting buildings (460 m2)
  • 2 Substations (235 m2)
  • Power station (220 m2)
  • Administrative building (720 m2)
  • Accommodation building (120 m2)
  • Guardhouse (17 m2)
  • Airside guardhouse (67 m2)
  • Water tank (525 m2)
  • Water treatment plant (2,314 m2)
  • Warehouse/office building (120 m2)
  • Chiller yard (350 m2)
  • Meteorology building (110 m2)
  • Equipment area (1,190 m2)
  • Security building (40 m2)
  • Weapons and ammunition depot (100 m2)
  • Permissions building (106 m2)
  • Meteorological hangar (7,316 m2)
  • Housing facility (160 m2)
  • Trained dogs facility (300 m2)
  • Bathrooms building (54 m2)
  • Mosque (670 m2)
  • Parking area (375 m2)

Dept. of Military Engineers

Engineering Authority

Egyptian Ministry of Defense & Military Production

Completed

Activities

Scope

Schematic Design

Detailed Design

Construction Supervision