Cairo International Airport Terminal Building 2 Renovation Program

Capacity upgrade to 7.5 mn passengers/year
 
<< Back
Print this case study

Cairo International Airport terminal building 2 is undergoing a major renovation effort to double its capacity to 7.5 million passengers per year. With a built-up area of 170,000 m2 the project comprises the renovation of the existing Terminal Building 2, the construction of new buildings which includes a new departure hall, and a new airside pier, doubling the existing total built-up area of TB 2.


The renovation program will also include a major upgrading and extension of the airside and landside pavements, involving more than 300,000 m2 pavement constructions.


The new terminal building size is based on IATA level of service B. The design peak hour capacity will be 3150 (2 way) international passengers.

Scope

  • Master plan
  • Infrastructure design
  • Concept design
  • Detailed design
  • Tender documents
  • Tender action
  • Construction management
  • Construction supervision

Types of activities

  • Architectural
  • Airfield lighting
  • Baggage handling system
  • Civil works
  • Communications and security systems
  • Electrical
  • HVAC
  • Mechanical
  • Structural

Click on thumbnail to change image.
Click on large image to view it at full resolution.

by DMICreative

Printed from the ECG website

Page: Sectors > Transport > Aviation > Cairo International Airport Terminal Building 2 Renovation Program
URL: http://www.ecgsa.com/cairointernationalairportterminalbuilding2renovati